Danish wind turbine manufacturer Vestas has received an order from China Guangdong Nuclear Wind Power Company for the delivery of 116 of its 850kW V52 wind turbines, bringing the total capacity of V52 wind turbines sold to the company to 500MW.
The agreement includes supply of the turbines, a VestasOnline Business supervisory control and data acquisition solution and a two-year maintenance and service agreement.
Lars Andersen, Vestas China managing director, said: "This latest sale, the eighth order from China Guangdong Nuclear Wind Power in the last 12 months, means that Vestas is now one of the largest single suppliers of wind turbines to the company."
Showing posts with label China Guangdong Nuclear Wind Power. Show all posts
Showing posts with label China Guangdong Nuclear Wind Power. Show all posts
Tuesday, December 30, 2008
Tuesday, October 21, 2008
Vestas Receives Order for 116 V52-850kW Turbines in China
Monday, Oct 20, 2008
Vestas has received an order for delivery of 116 V52-850kW wind turbines for Suniteyou Wind Farm III and IV, Xilinguole City, Inner Mongolia Province, China. The order was received from China Guangdong Nuclear Wind Power.
The contracts include supply and commissioning of the turbines including towers, the VestasOnline Business supervisory control and data acquisition solution and a two-year service and maintenance agreement.
Delivery and commissioning of the turbines is planned for the third quarter of 2009.
Lars Andersen, managing director of Vestas China, said: We are very pleased about this order; the fact that China Guangdong Nuclear Wind Power has once again selected Vestas turbines is proof of both the quality of our product and the overall business case of our wind energy solutions.
Vestas has received an order for delivery of 116 V52-850kW wind turbines for Suniteyou Wind Farm III and IV, Xilinguole City, Inner Mongolia Province, China. The order was received from China Guangdong Nuclear Wind Power.
The contracts include supply and commissioning of the turbines including towers, the VestasOnline Business supervisory control and data acquisition solution and a two-year service and maintenance agreement.
Delivery and commissioning of the turbines is planned for the third quarter of 2009.
Lars Andersen, managing director of Vestas China, said: We are very pleased about this order; the fact that China Guangdong Nuclear Wind Power has once again selected Vestas turbines is proof of both the quality of our product and the overall business case of our wind energy solutions.