Huaneng Wenchang Wind Power project is on the track, 11 sets of wind turbines have been installed, and the first phase project will be completed by the end of 2008. The total capacity for the first phase Huaneng Wenchang Wind Power project is 49.5MW, and in total 33 sets of 1.5MW wind turbines will be installed, and the wind turbines are manufactured by Sinovel. The first phase project will be able to generate about 103 million KWH power per year.
Huaneng Wenchang Wind Power project is the first wind power project in Hainan province, and the total planned capacity is 120MW, and the total investment is 1.3 billion CNY.